COST COMPARISON

The supply and install cost of a TECSLAB™ floor system is very competitive against traditional concrete frame structures, as demonstrated in the following comparative case study of two different apartment projects. In each case, a Quantity Surveyor assessed two equivalent structural designs for each building – timber vs concrete. Savings were demonstrated against multiple items including; floor supply and install, preliminaries costs such as pumps, formwork etc., footings size, labour costs (domestic chippies) and considerable time savings.

▼ CASE A; 79 Apartments over 4 storeys above basement car park

▼ Case B; 5 Apartment development over 3 storeys above basement car park

▼ SAVINGS RESULTS 1 - TECSLAB v conventional structure

▼ SAVINGS RESULTS 2 - 15-30 Percent Saving

DOWNLOAD COST COMPARISON CASE STUDY